Most confusion in a remodel comes from a few words: an allowance (a placeholder budget for items you pick later), a change order (a written change to scope and price), a lien waiver (a release that a contractor or supplier has been paid), and in cost reports, the share of cost recouped (how much of the job cost agents think it adds at resale). This page defines those and about 20 more in plain English.

Quotes and contracts use trade shorthand. Knowing these words lets you compare quotes on the same terms and spot what a contract leaves out.

## Quote and contract terms

AllowanceA placeholder amount in a quote for items you will choose later, such as tile or light fixtures. If your choice costs more, the price goes up. Low allowances can make a quote look cheaper than it is. Change orderA written change to the scope, price or schedule, signed by you and the contractor before the extra work starts. ContingencyMoney you set aside, outside the contract price, for surprises such as rot or old wiring found when walls open. It is your planning choice, not a fee. Our [budget calculator](https://remodelcostfacts.com/planning/remodel-budget-calculator/) starts at 10% as an editable setting. Draw schedule (payment schedule)When you pay, and how much. A schedule tied to finished stages of work protects you better than one tied to dates. RetainageA share of the price held back until the job is fully finished, including punch-list items. Punch listThe list of small items to fix or finish before final payment. Lien waiver (lien release)A signed statement that a contractor, subcontractor or supplier has been paid and gives up its right to file a lien on your home for that amount. Rules on liens differ by state. Mechanic's lienA legal claim against a property by someone who worked on it or supplied materials and was not paid. It can be filed even if you paid your general contractor, if the contractor didn't pay a supplier, which is why lien waivers matter. Scope of workThe written description of exactly what will be done and with what materials. Comparing quotes only works when the scopes match. License, bond and insuranceThree different things. A license is permission from the state or locality to do the work; a bond is a guarantee that can pay claims if the contractor fails to meet certain obligations; liability insurance covers damage the contractor causes. See your [state's licensing rules and lookup](https://remodelcostfacts.com/states/).

## Permit and code terms

Building permitApproval from your city or county before certain work starts, followed by inspections. See [do I need a permit](https://remodelcostfacts.com/planning/do-i-need-a-permit-to-remodel/). IRC R105.2The section of the International Residential Code that lists work exempt from a permit, such as painting, tiling, cabinets and countertops. Local governments adopt and amend it. Final inspectionThe last inspection that closes the permit. Make final payment depend on it passing.

## Cost report terms

Job costIn the Cost vs. Value Report, the estimated price of a defined project, built to a published specification, in a given region. Resale valueHow much real estate professionals surveyed for the report think the project adds to a home's value at sale. Cost recoupedResale value divided by job cost. Over 100% means the project, on average, adds more value than it costs. Midrange and upscaleThe report's two finish levels. Midrange uses standard, mid-priced materials; upscale uses premium materials and often enlarges or reconfigures the space. Minor vs major kitchen remodelA minor remodel keeps the cabinet boxes and layout of a 200-square-foot kitchen; a major one replaces everything and adds an island. See [kitchen remodel cost](https://remodelcostfacts.com/kitchen/kitchen-remodel-cost/).

## Roof, window and siding terms

Square100 square feet of roof (or siding) surface. Roofers price per square. Tear-offRemoving the old roofing down to the deck before installing new roofing, as opposed to laying a new layer over the old. Pitch (slope)How steep a roof is, written as inches of rise per 12 inches of run, such as 6 in 12. Steeper roofs have more area for the same footprint; our [roof calculator](https://remodelcostfacts.com/roofing/roof-replacement-cost-calculator/) does the math. Standing seamMetal roofing made of long panels joined by raised, interlocking seams. Double-hung windowA window with two sashes that both slide up and down. The Cost vs. Value window projects use 3 x 5 foot double-hung units. Fiber-cement sidingSiding boards made with cement and fibers, an alternative to vinyl or wood. Compared with vinyl in [siding replacement cost](https://remodelcostfacts.com/roofing/siding-replacement-cost/). Universal designDesign that works for people of all ages and abilities, such as a curbless shower, grab bars and wider doorways.

## Frequently asked questions

What is an allowance in a remodeling contract?

A set amount the contractor includes for items not yet chosen, such as tile, fixtures or lighting. If you pick something that costs more, you pay the difference, so check that allowances match what you actually plan to buy.

What is a change order?

A written, signed change to the contract's scope, price or schedule. Ask for one before any extra work starts, so the price is agreed in writing.

What does cost recouped mean?

In the Cost vs. Value Report, the resale value a project adds divided by its job cost. A project that costs $20,000 and adds $15,000 of value recouped 75%.

How big is a roofing square?

100 square feet of roof surface. A 3,000-square-foot roof, the size priced in the Cost vs. Value Report, is 30 squares.

## Related guides

[Is my remodeling quote fair? Quote checkerCompare a contractor's quote with the 2025 average for the same project in your region.](https://remodelcostfacts.com/planning/remodel-quote-checker/)[Do I need a permit to remodel?What finish work is usually exempt, what needs a permit, and how to check with your building department.](https://remodelcostfacts.com/planning/do-i-need-a-permit-to-remodel/)[Which remodeling projects add the most resale value?All 28 projects in the 2025 report, ranked by how much of their cost they add back at resale.](https://remodelcostfacts.com/planning/remodeling-projects-roi/)[Contractor licensing and remodeling costs by stateWho licenses contractors in your state, the license lookup, and regional 2025 costs.](https://remodelcostfacts.com/states/)

## Sources

1. [JLC, 2025 Cost vs. Value methodology](https://www.jlconline.com/cost-vs-value/2025/methodology), checked 2026-11-27
2. [JLC, Cost vs. Value project descriptions: windows, roofing, siding](https://www.jlconline.com/cost-vs-value/project-descriptions?o=3), checked 2026-11-27
3. [JLC, Cost vs. Value project descriptions: kitchens](https://www.jlconline.com/cost-vs-value/project-descriptions/?o=2), checked 2026-11-27